1 September 2015 - Projects update and handover - France
At the site of the Paluel nuclear power plant (Normandy), after two years of works, Eurovia’s Dieppe office has completed its development of a 90,000 sq. metre area served by heavy-duty roadways and the various utility networks. These works form part of EDF’s Major Overhaul (Grand Carénage) programme, aimed at extending the life of its nuclear installations in France. As a result of this project, this Eurovia office now has 35 employees qualified to work on a nuclear site.