16 May 2011 - New contracts - Germany

Eurovia has won the contract to redevelop the Schwanebeck interchange, the meeting point, to the north of the city, of the A10 motorway, the Berlin “Ring” (orbital motorway) and the A11 motorway. The project concerns the widening of this structure (from 2x2 to 2x3 lanes) in order to improve traffic flows. In particular, it will involve eliminating the nearby Weißensee interchange, the creation of nine engineering structures, the refurbishment of a 3 km section on both the A10 and the A11, 1.15 million cu. metres of earthworks and the laying out of 25,000 m of rainwater drainage channels. The works will be carried out by a consortium comprising Eurovia Verkehrsbau Union, Eurovia Beton and Eurovia Industrie.
They start in early May, with handover sche­duled for 2013. Contract value: €32m.