Le premier tunnelier du Grand Paris Express en route vers son chantier

The first TBM for the Grand Paris Express heading to its worksite

In connection with the works on section T3C of Line 15 South of the Grand Paris Express – awarded to VINCI Construction (VINCI Construction Grands Projets, leader, VINCI Construction France, Dodin Campenon Bernard and Botte Fondations) and Spie Batignolles – the first S-1119 earth pressure balance tunnel boring machine (external diameter: about 10 m) is to leave the plant of manufacturer Herrenknecht, in Germany, and head for the worksite.

The first component will arrive in mid-September 2018, and the tunnelling westwards, starting out from the Parc Robespierre shaft (92), should begin early in 2019. A second TBM will be needed to drive the 8.2 km of tunnel of the same works package between the Fort d’Issy – Vanves – Clamart and Villejuif – Louis Aragon stations.