2024 Universal Registration Document

General and financial elements

Security interests connected with financing

Collateral security (in the form of pledges of shares and mortgages on land and buildings) is generally provided to secure financing granted to subsidiaries, and breaks down as follows:

(in € millions) Start date End date Amount
London Gatwick airport (United Kingdom)

London Gatwick airport (United Kingdom)

Start date

2011

London Gatwick airport (United Kingdom)

End date

2049

London Gatwick airport (United Kingdom)

Amount

2,749

Aerodom (Dominican Republic)

Aerodom (Dominican Republic)

Start date

2024

Aerodom (Dominican Republic)

End date

2034

Aerodom (Dominican Republic)

Amount

586

Arcour (France)

Arcour (France)

Start date

2008

Arcour (France)

End date

2047

Arcour (France)

Amount

556

OMA (Grupo Aeroportuario del Centro Norte – Mexico)

OMA (Grupo Aeroportuario del Centro Norte – Mexico)

Start date

2022

OMA (Grupo Aeroportuario del Centro Norte – Mexico)

End date

2030

OMA (Grupo Aeroportuario del Centro Norte – Mexico)

Amount

411

Arcos (France)

Arcos (France)

Start date

2018

Arcos (France)

End date

2045

Arcos (France)

Amount

351

Lima Expresa (Peru)

Lima Expresa (Peru)

Start date

2016

Lima Expresa (Peru)

End date

2037

Lima Expresa (Peru)

Amount

349

Belgrade airport (Serbia)

Belgrade airport (Serbia)

Start date

2018

Belgrade airport (Serbia)

End date

2035

Belgrade airport (Serbia)

Amount

262

ADL - Aéroports de Lyon (France)

ADL - Aéroports de Lyon (France)

Start date

2016

ADL - Aéroports de Lyon (France)

End date

2033

ADL - Aéroports de Lyon (France)

Amount

192

Concessionária dos Aeroportos da Amazônia (Brazil)

Concessionária dos Aeroportos da Amazônia (Brazil)

Start date

2022

Concessionária dos Aeroportos da Amazônia (Brazil)

End date

2046

Concessionária dos Aeroportos da Amazônia (Brazil)

Amount

112

Other concession companies

Other concession companies

Start date

 

Other concession companies

End date

 

Other concession companies

Amount

420

Total TotalStart date  TotalEnd date  Total

Amount

5,989

Other security interests related to the funding of concession projects have been granted in an amount of €912 million, the vast majority of which concern Lima Expresa in Peru and Northwest Parkway in Denver, in the US state of Colorado.

15.2 Companies accounted for under the equity method

Contractual investment obligations

At 31 December 2024, the Group’s share of the investment undertakings made by these companies amounted to €445 million as opposed to €927 million at 31 December 2023. The decline in these commitments is mainly due to the suspension of the Rift Valley project in Kenya, partially offset by new commitments undertaken for Budapest airport in 2024.

Collateral security connected with financing

Collateral security has been granted in the form of pledges of shares in companies accounted for under the equity method.

The net carrying amount of the shares pledged at 31 December 2024 was €125 million (€34 million at 31 December 2023) and included shares in Olympia Odos (the company operating the toll motorway currently connecting Elefsina, Corinth and Patras in Greece) for €74 million, SMTPC (the holder of the concession for the Prado Carénage road tunnel in Marseille) for €26 million, and WVB East End Partners (the company holding the concession for the Ohio River Bridges – East End Crossing project in the United States) for €15 million.

In addition, €114 million of corporate guarantees were granted, including those granted by Cobra IS to the banks financing high-voltage line projects in Brazil for €70 million.

Funding commitments

The Group has made commitments to provide funding (capital and/or subordinated loans) to companies accounted for under the equity method. At 31 December 2024, those commitments amounted to €47 million (€54 million at 31 December 2023). They mainly concern the D4 motorway project in the Czech Republic (€26 million) and the B247 federal road project in Germany (€11 million).